The work done in lifting a mass of 2000 kg vertically to a height of 40 metres is
- 392.4 kJ.
- 784.8 kJ.
- 196.2 kJ.
Explanation from PART66Online
Work against gravity is mgh = 2000 kg x 9.81 m/s squared x 40 m = 784,800 J = 784.8 kJ. The 392.4 kJ distractor comes from omitting a factor or using half the height, but the full mass and height apply here.
jawwadbaig asked · 20 Oct 2012
how?
Community Comments (1)
F=mg
2000x9.8
=19600
then find work with height 40m
W=force x distance
W=19600x40
=784000J or 784kJ
Please Sign In to post a comment.
More discussions in 2. Physics
- The work done in lifting a mass of 2000 kg vertically to a height of 40 metres is
- How would you work out the work done by a machine assuming it is 100% efficient?
- Ignoring friction, if you let an object slide down a slope, at the bottom
- A force of 15N is needed to move a body of mass 30kg along a footpath with uniform velocity. Find the coefficient of dynamic friction.(take g as 10m/s/s).
- A mass of 400kg moves 27 metres with a force of 54N. What is the work produced?
- If you push an object with a force of 5 N for 10 m in 4 seconds, how much power is used?